Building Consultancy – Vax Limited: Two Colmore Square, Birmingham

PROJECT SUMMARY: Fit-out of 23,680 sq ft of level f floor-plate
PROJECT VALUE: £425,000
TIMESCALE: 12 weeks

Having been tasked with project managing the fit-out of a fifth-floor office in Birmingham city centre, the building consultancy team negotiated costs, oversaw a tender for furniture suppliers and specification strategy and monitored the entire process from start to finish.

The building consultancy team established the scope and cost of the works, agreed the precise locations of electrical power and data-floor box locations to suit the client’s required furniture layout.

SERVICES

  • LIAISON BETWEEN CLIENT, LANDLORD AND CONTRACTORS
  • OVERSEEING FURNITURE TENDER PROCESS
  • OVERSEEING FURNITURE SPECIFICATION STRATEGY
  • MONITORING OF WORKS THROUGHOUT
  • LANDLORD CAT B SCOPE AND COST NEGOTIATIONS